Construction is progressing well. Block 1 and 2 are finished up to the fourth level. Foundations are finished for Block 3, with the ground floor slab under construction. Deliveries are expected to be completed by December 31, 2028—right on schedule. Click below to see a short video with some recent images from the site. Construction […] Read more